CALIFORNIA LAWS on CONDITIONAL and UNCONDITIONAL
PROGRESS PAYMENT and FINAL PAYMENT
STATUTORY MECHANICS LIEN RELEASE FORMS
Four Types of Statutory California Mechanics Lien Waiver and Release Forms
1. Conditional Mechanics Lien Waiver and Release Upon Progress Payment
- Contractor and Subcontractors Submit with Progress Payment Application
2. Unconditional Mechanics Lien Waiver and Release Upon Progress Payment
- Contractor and Subcontractors Submit After Receipt of Prior Progress Payment
3. Conditional Mechanics Lien Waiver and Release Upon Final Payment
- Contractor and Subcontractors Submit with Final Payment Application
- Be Careful to State and Include Amount of Disputed Claims Not Covered by Release
4. Unconditional Mechanics Lien Waiver and Release Upon Final Payment
- Contractor and Subcontractors Do not Provide Unless Fully Paid for All Work
Scope of Mechanics Lien Waiver and Release Forms
¬ Only the above mentioned statutory forms of Waiver and Release Forms are permitted
under the law to waive rights to record a mechanics lien.
¬ Mechanic’s lien, stop notice and bond rights cannot be waived by provisions contained in
a contract or by using other forms of release.
¬ Waiver and Release Forms DO NOT release Breach of Contract etc claims, or claims
for: . Rescission
¬ Abandonment
¬ Breach of Contract
¬ Fraud Claims
¬ Tort Claims
Waiver and Release Forms - Extra Work Claims Not Reserved in Lien Release Forms
¬ If there was an Executed Change Order as of date of release - Claim is Released
¬ If there were unsigned Oral Change Orders as of date of release - Not Released
¬ BE VERY CAREFUL IN FILLING IN and EXECUTING THESE FORMS!
New Mechanics Lien Release Forms Must be Used Effective July 1, 2012.
Please be aware that as part of recent wholesale changes made to the Mechanics Lien,
Stop Notice and Payment Bond laws by the General Assembly, effective July 1, 2012 there are
new forms for Conditional and Unconditional Lien Releases on Progress Payments and Final
Payments. (See Civil Code §§ 8132-8138, below.)
The last time the Legislature made changes in these forms, one court held that a
contractor or owner who did NOT use the new forms after their effective date did NOT
obtain a valid lien release!!!
CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT NOTICE: THIS