DDC – SAMPLE C&D WASTE MANAGEMENT PLAN
June 2003
SAMPLE WASTE MANAGEMENT PLAN
A sample C&D Waste Management Plan appears on the following pages. It indicates the topics to be
covered and the type of information that would be appropriate. Dummy information has been included to
illustrate the Plan.
SAMPLE WASTE MANAGEMENT PLAN
This is a Sample Waste Management Plan. You may use this as a guide in developing your own.
Contractor: Very Best Construction Company Prepared May 1, 2003 / Revised July 3, 2003
Project: Renovation/Addition to Big Building, Queens, N.Y.
Designated Recycling Coordinator: Joe Doe
Waste Management Goals
· This project will recycle, reuse or salvage at least 75%, by weight, of the waste generated on site.
Waste Prevention Measures
· Five large rooms on the 1
st
Floor, near the service elevator, have been designated for storage of delivered
material and equipment until it is needed. These rooms are dry and lockable. Each Prime Contractor has been
assigned one of these rooms.
· Reusable metal forms will be used for the concrete structural elements.
· Each major vendor will be sent a letter requesting their cooperation in planning for minimal or take-back
packaging, and just-in-time delivery. The Recycling Coordinator will provide a draft letter to each Prime
Contractor for their use.
· A mock-up of the ceiling, soffit, ductwork and lighting shown on detail xyz will be built for coordination and
review before proceeding with this work.
Reuse and Salvage Items (Included on the chart below)
· The paneled doors from the existing offices will be reused per the documents.
· Excavation rock will be crushed and used as fill on site.
· Shelving removed from the library will be donated to Dick and Jane School
Communication Plan
· Waste prevention and recycling activities will be discussed at each job meeting.
· The recycling coordinator will give each contractor and subcontractor a copy of the Waste Management Plan,
provide instruction in appropriate separation and handling procedures and show them the recycling areas.
· Prime contractors will be expected to make sure that their workers comply with the Waste Management Plan.
· All recycling containers will be labeled in English and Spanish, with acceptable / unacceptable materials posted.
Each sign will have a representative picture of the materials to be recycled.
· If methods or container locations change during the course of the project, the Recycling Coordinator will notify
each contractor and subcontractor in writing.
Contamination Prevention Measures
· Small roll-off containers convenient to work areas will be used; Very Best Contracting will periodically
consolidate the contents in the appropriate dumpsters. Garbage containers for non-recyclable materials will be
located adjacent to recycling containers.