AUSTIN WATER CONSTRUCTION PLAN INFORMATION
AND SUBMITTAL REQUIREMENTS CHECK LIST
EFFECTIVE August 9, 2022
Below are the items, which do not meet minimum requirements for subdivision construction
plans to pass the Land Use Review completeness check process. The information outlined
below can be found in the Utility Criteria Manual Sections 2.5 through 2.9.4, Standard
Specifications, Standards Manual and the Site Plan Application Instructions. All deficiencies
below (both bold and non-bold) shall be addressed to achieve compliant completeness check.
GENERAL REQUIREMENTS
❑ All plat, preliminary plans, site plan and subdivision construction cases shall be submitted in
PDF (.pdf) format to allow electronic review by AW. Any other file types will be rejected.
❑ Engineer's dated signature and seal of a Professional Engineer licensed in the State
of Texas on each plan sheet and including the engineering firm name and Texas
registration number (Title 22 TAC §137.33 and §137.77).
❑ Project title; date of plans and revisions.
❑ Indicate on the cover sheet, the subdivision file number and show all required permit
numbers such as development permit, Texas Department of Transportation permit,
railroad crossing permit, etc.
❑ A general location map with street names, showing MAPSCO and grid numbers.
❑ An index on the cover sheet or on the 2nd sheet of the drawings.
❑ North arrow and scale must be shown. The standard horizontal scale for plan and
profile sheets shall be 1″ = 40′, 30′ or 20′ for the plan view. The vertical scale shall be
1″ = 4′, 3′ or 2′, respectively. The same scale shall be used on all plan and profile
sheets. All Texas Department of Transportation design build projects, Capital
Improvement Projects, and General Permit projects shall be 1” = 20’ horizontal scale
for the plan view. For sheets other than plan and profile, horizontal scales of 1″ = 40′,
30′ or 20′ may be used as appropriate. Where relevant and applicable, a scale of 1” =
10’ for plan views and a scale of 1” = 1’, 2’, 3’, 4’, or 5’, as needed to fit the area on the
page and provide the most clarity for profiles, shall be used for detailed water,
reclaimed water, and wastewater connections, designs, utility crossings, and/or
special detail drawings. The minimum size for plan and profile sheets shall be 22″ ×
34″. Plan view and associated profile shall appear on the same sheet with the plan
view at the top half of the sheet.
❑ Copy of recorded final plat or land status determination letter/report; or, with Pipeline
Engineering approval, an approved final plat case (awaiting recording).
❑ Include current version of the Austin Water General Information and Construction
Notes for Commercial Sites and Subdivision Plans sheet for stamps, latest Standard
Austin Water Construction Notes, approved Service Extension Request
documentation, meters, fire flow tests etc. All boxes from this sheet must be included
for submittal. With the exception of providing the required information, do not remove,
revise or reduce any text, Title Block, or tables on this sheet without prior authorization
from Austin Water Pipeline Engineering. For current version of required AW General
Info Sheet and other documents, please visit http://austintexas.gov/page/pipeline-
engineering
❑ Design for SER required water, reclaimed water, and wastewater shall be included in
construction plan submittal
❑ All plans shall provide available fire demand at 20 psi in gallons per minute (GPM)
(Not “flow rate” from the fire flow test) pursuant to the current International Fire Code
(IFC) on the Austin Water General Information and Construction Notes for Commercial